Cabinet Division Employees Co-operative Housing Society

Overview

The officials of the Cabinet Division, Government of Pakistan, got together some years ago and founded their own organization in order to provide decent and affordable housing to its members, and registered it with the government as the Cabinet Division Employees Cooperative Housing Society Regd. (CDECHS).

Initially the CDECHS was meant for making plots available only to employees of the Cabinet Division but later on persistent public pressure, the Society opened for its membership to employees of all ministries/divisions in Islamabad. Recently it has reserved 20 percent of the available plots for private citizens too. Presently it is one of the prime housing societies in Islamabad.

Town Planning:

In view of the privileged location of the CDECHS in the main housing sectors of Islamabad, the Society is bound to follow the rules and regulations prescribed for purpose of town planning by the Capital Development Authority (CDA). The CDA has already granted the Society permission for scheme development vide its No. CDA/PLW-UP (90) Cab. Div. /ECHS/93/3773 dated 23 December 1993.

Broadly speaking, the Society will arrange all basic facilities, such as primary and secondary school/parks, healthy centres, a community centre, mosque, commercial areas, playgrounds, a sports club and a graveyard. The development of the housing scheme will cover provision of utilities like electricity, gas, independence water supply and a proper drainage and sewerage system. Connection points to all of the utilities will be provided at each door step of the developed plot.

4113161-0_4113161-2311807_s - Copy

Features

1.0         ROAD WORKS

1.1    Earth Work In Cutting/Filling

The work is done during this month on street #26A, 29A in sector . E-17. The measured progress of this month is 0.08%.The total up to date progress is 75.83%.

1.2    Sub-grade Preparation

The work is done during this month on street #26A, 29A and in sector E-17.The total up to date progress is 75.81%.

1.3    Sub-Base Course

65.93% of the total work has been completed. The work done during the month on street#20, 4, 6A, 26A in sector E-16/3 and E-17.The progress measured during the month is 0.65%.

1.4    Aggregate Base Course

0.54% work is done during this month on street #20 in sector E-16/3 and st#4, 6A in sector E-17. The up to date progress is measured 65.37% of the total work.

1.5    Prime Coat

The prime coat spray is carried out on M-2 and major road in sector E-16/3 . The progress measured during the month is 0.74% and up to date progress is 63.93%.

1.6    TST

No further activity has been carried out under the TST head. The previous up to date progress is 54.57%.

1.7    Wearing Course

The asphalt wearing course work is carried out on M-2 and major road. The progress achieved during the month is 1.47% and the total upto date progress is 62.89%.

1.8    Curb Stone Fixing

No work during the month has been noticed. Up to date progress is retained 68.53. %

1.9    Drainage Work

The drainage work has been completed during this month along the
Street#12 up 250 ft in length and M-3 up to 200 ft in length, in sector E-17 and E-16/3 respectively.

2.0    SEWERAGE SYSTEM

2.1    Excavation

73.23% of the total work has been completed. Excavation was made for Sewerage work along Street No. 21, 28 and 30 in sector E -16/3. The progress was measured for the month is 0.69%.

2.2    Backfilling

72.38% of the total work is completed. The progress gain for this month is 1.16%.

2.3    Manhole Construction

Manholes are constructed during the month along the street no. 30, 28 and 21 in sector E-16/3. It has been completed up to 71.09% and progress for the month achieved is 1.02%.

2.4    Sewerage Network

72.41% of the total work has been completed. During the month progress was measured 0.74%. Work has been carried out along the Street No.30, 28 and 21 in sector E-16/3.

2.5     Structural Works (Box Culvert)

Out of 15 Nos. proposed Box culverts 9 Nos. have so far been completed in the land already in possession. The remaining 6 Nos. are proposed in the extended, the possession yet to be taken over. No work during the month.

3.0    WATER SUPPLY NETWORK

3.1    Excavation / Backfilling

74.75% of the total work has been completed. Excavation was made for Water supply work along Street No. 28, 21,36 and 35 in sectors E -16/3.The progress was measured for this month is 0.74%.

3.2     Water Supply Network

74.21% of the total work has been completed during the month and progress for the month was measured 0.68%. Work has been carried out along the Street No. 28, 21,36 and 35 in sectors E -16/3 .

4.0    O/H & U/G WATER TANKS

4.1    Construction of U/G Water Tank

The 03 Nos. underground water tanks each of 100,000 gallon capacity have been completed 100% only accessories are remaining. Providing and laying of terrazzo lining in the underground water tank is completed.

4.2    Construction Of O/H Water Tank

Structural work for the total 03 Nos. of OHWT has been 100% completed. Terrazzo lining inside of the tank bowl at tank no. 2 and 3 in sector E-16/2 and E-16/3 respectively has been completed and further terrazzo lining work is in progress at tank No. 01 in sector E-17/3 and approximately 100% lining work of tank#01 is completed.

5.0    ELECTRICAL WORKS

Tender for pre-qualification of contractors for under-ground laying of electricity cables is under process.

6.0    SUI GAS WROKS

The laying of Sui gas pipe lines dia 4” length 2KM was continued during the month at different roads in sectors E-16/3 & E-17. Mostly work was continued at main approach road to lay the main line of dia 6”. The interconnection of the lines and testing will be done after the completion of the pipe lay.